2014-03-06: Fixed AUG MGI AREAD data 2014-03-04: Uploaded AUG MGI NPARTSPK1 data 2013-09-26: Uploaded AUG MGI additions (TIMESPK & VOLD) 2013-09-09: Uploaded D3D MGI NPARTSPK1 data 2013-09-03: Uploaded initial AUG MGI data to database 2013-04-03: Cleaned up invalid MAST MGI values 2013-02-19: Uploaded initial CMOD MGI data to database 2013-02-05: Uploaded Aditya general data to database. 2012-03-06: Uploaded JET, MAST, & JT-60U MGI data to database. 2012-03-05: Added new variables (INTLI3D, DENSSPK5, CONTROLSHOT) to database 2012-01-24: Videoconference Minutes Attendees: N. Eidietis, E. Hollmann, A. Hyatt, M. Lehnen, G. Pautasso, R. Raman, F. Saint-Laurent, M. Sugihara 1. Procedural notes from N. Eidietis
- Authoritative IDDB variable list is on website... please use that for reference
MDSplusVar
- Please use standard Excel form for data submission:
DataSubmission
- Thanks to JET (Lehnen) & MAST (Andrew Thornton) for submission
- New data will be uploaded to IDDB before March 2012 ITPA
- Will improve default SQL query & examples so that SQL is more self explanatory
2. Should INTLID & RMAGD be required variables?
- Agreed without objection.
3. Should control shot without mitigation be included for comparison to mitigated shots?
- Agreed in principle. However, it is believed that such control shots are very rare except
in VDE cases. A new variable, CONTROLSHOT, will be added to the MGI portion of IDDB.
4. Proper density measurement interval
- Instantaneous density measurements deemed very noisy. Adding new variable DENSSPK5 to
average the density from the current peak (TIMESPK) to the 50% point of the CQ (TIME5).
5. Data submission status
- JET, MAST data in
- TEXTOR coming, but diagnostics very limited
- AUG will have some submissions in February
- Tore Supra data submission delayed until after March
6. Ending note
- R. Raman suggested that we should consider adding measurements of the SOL
(thickness, density, temperature) at a later time.
|
©2013 General Atomics All Rights Reserved |